03.
THE CHALLENGE
Basement construction requires careful sequencing, particularly where deep excavation, restricted access and neighbouring structures are involved.
Plant movements, material deliveries and concrete operations had to be coordinated around the available working space while maintaining safe access throughout the works.
Particular attention was also required at below-ground interfaces to ensure the reinforced concrete construction, drainage and waterproofing systems were correctly coordinated before concrete placement.
04.
OUR APPROACH
The basement was constructed using a carefully planned sequence, allowing excavation and structural works to progress safely and efficiently.
Following excavation and formation preparation, the below-ground drainage and waterproofing requirements were coordinated before reinforcement was installed for the basement slab.
The reinforced concrete retaining walls were then constructed using engineered reinforcement and formwork systems, with concrete pours planned to maintain quality and continuity throughout the structure.
South East Formwork coordinated excavation, reinforcement, formwork and concrete operations as a single package, reducing interfaces between different trades and allowing greater control over the construction programme.