01.

PROJECT OVERVIEW

South East Formwork was appointed to undertake the groundworks and reinforced concrete package for the construction of a new residential basement.
The project was neighboured by properties on both sides, which meant piling was needed to hold back the ground in a temporary state before excavation could begin. Construction of the below-ground structure, requiring careful coordination of excavation, temporary works, drainage, waterproofing and reinforced concrete operations.
Our team managed the works from the initial excavation through to completion of the reinforced concrete basement structure, providing the client with a coordinated structural and groundworks package.
02.

SCOPE OF WORKS

South East Formwork works included:
Site setup and preparation
Reduced-level and bulk excavation
Muck-away and disposal of excavated material
Temporary excavation support and associated works
Groundwater management during construction
Below-ground drainage
Formation and preparation
Reinforced concrete foundations
Reinforced concrete basement floor slab
Reinforced concrete retaining walls
Reinforcement fixing
Formwork and shuttering
Waterproof concrete placement and finishing
Service penetrations and associated detailing
03.

THE CHALLENGE

Basement construction requires careful sequencing, particularly where deep excavation, restricted access and neighbouring structures are involved.
Plant movements, material deliveries and concrete operations had to be coordinated around the available working space while maintaining safe access throughout the works.
Particular attention was also required at below-ground interfaces to ensure the reinforced concrete construction, drainage and waterproofing systems were correctly coordinated before concrete placement.
04.

OUR APPROACH

The basement was constructed using a carefully planned sequence, allowing excavation and structural works to progress safely and efficiently.
Following excavation and formation preparation, the below-ground drainage and waterproofing requirements were coordinated before reinforcement was installed for the basement slab.
The reinforced concrete retaining walls were then constructed using engineered reinforcement and formwork systems, with concrete pours planned to maintain quality and continuity throughout the structure.
South East Formwork coordinated excavation, reinforcement, formwork and concrete operations as a single package, reducing interfaces between different trades and allowing greater control over the construction programme.
05.

THE RESULT

The completed works created a substantial reinforced waterproof concrete basement structure ready for the subsequent stages of the residential development.
By undertaking the principal groundworks and structural concrete elements within one package, South East Formwork provided the client with a single specialist contractor responsible for the key below-ground construction activities.
The project demonstrates our ability to deliver technically demanding basement construction involving significant excavation, reinforced concrete and associated groundworks.