THE CHALLENGE - WATER INGRESS
One of the principal challenges throughout the project was the site's close proximity to the lake.
Groundwater and water ingress therefore remained an important consideration during the foundation works.
The excavation and pile-cap construction sequence had to account for changing ground and water conditions, with water management maintained throughout the works to provide suitable conditions for reinforcement, formwork and concrete placement.
This was particularly important during preparation for concrete pours, where the foundation excavations needed to remain appropriately controlled and ready for construction.
04.
OUR APPROACH
South East Formwork coordinated the reinforcement, formwork, holding-down bolt installation and concrete operations to meet the demanding tolerances required for the roller coaster foundations.
Each pile cap was prepared and reinforced before the holding-down bolt assemblies were accurately positioned in accordance with the structural requirements.
Formwork was then completed and the foundations checked to high tolerance in preparation for the concrete pours.
Close coordination between the site teams was essential to ensure that reinforcement congestion, holding-down bolts, formwork and concrete placement could all be successfully accommodated within the substantial foundation structures.