01.

PROJECT OVERVIEW

South East Formwork was appointed to undertake the formwork and reinforcement package for the foundations of Hyperia, Thorpe Park's major roller coaster development.
The works involved the construction of large reinforced concrete pile caps and structural foundations designed to support the substantial loads generated by the roller coaster structure.
Working alongside the lake and within an active theme park environment presented a number of logistical and technical challenges, requiring careful planning throughout the construction process.
02.

SCOPE OF WORKS

Our works included:
Formwork and shuttering to large reinforced concrete pile caps
Reinforcement fixing
Preparation of pile heads and foundation areas
Construction of heavily reinforced pile caps
Installation and positioning of large holding-down bolt assemblies
Coordination of holding-down bolts with reinforcement and formwork
Concrete pour preparation
Concrete placement and associated works
Management of water ingress during construction
Coordination with other contractors and the roller coaster installation requirements

LARGE REINFORCED CONCRETE PILE CAPS

A significant part of the package involved constructing large, heavily reinforced pile caps forming the foundations for the roller coaster's structural supports.
The size of the foundations and reinforcement requirements demanded careful planning of the fixing and formwork operations before each concrete pour.
Accuracy was particularly important because the foundations incorporated large holding-down bolts used to secure the roller coaster structure.
The bolt assemblies had to be accurately positioned and maintained during reinforcement installation and concrete placement to ensure the subsequent steel structure could be installed correctly.

KIOSK BASES & SPLASH-THROUGH AREA

In addition to the main ride foundations, South East Formwork constructed high-level concrete bases for kiosk structures associated with the development.
Our package also included the RC walls forming the splash-through area, adding another technically demanding element to the works and requiring careful coordination with the surrounding ride infrastructure.
03.

THE CHALLENGE - WATER INGRESS

One of the principal challenges throughout the project was the site's close proximity to the lake.
Groundwater and water ingress therefore remained an important consideration during the foundation works.
The excavation and pile-cap construction sequence had to account for changing ground and water conditions, with water management maintained throughout the works to provide suitable conditions for reinforcement, formwork and concrete placement.
This was particularly important during preparation for concrete pours, where the foundation excavations needed to remain appropriately controlled and ready for construction.
04.

OUR APPROACH

South East Formwork coordinated the reinforcement, formwork, holding-down bolt installation and concrete operations to meet the demanding tolerances required for the roller coaster foundations.
Each pile cap was prepared and reinforced before the holding-down bolt assemblies were accurately positioned in accordance with the structural requirements.
Formwork was then completed and the foundations checked to high tolerance in preparation for the concrete pours.
Close coordination between the site teams was essential to ensure that reinforcement congestion, holding-down bolts, formwork and concrete placement could all be successfully accommodated within the substantial foundation structures.
05.

THE RESULT

The completed reinforced concrete pile caps provided the substantial foundations required to support the Hyperia roller coaster structure.
The project demonstrates South East Formwork's ability to undertake large-scale, technically demanding reinforced concrete packages, including heavily reinforced foundations, complex formwork and accurately positioned structural holding-down bolts.
It also demonstrates our capability to deliver specialist concrete works where challenging ground conditions, water ingress, tight tolerances and coordination with major structural installations are critical to the successful completion of the project.

VIEW MORE PROJECTS

CONTACT US

HAVE A COMMERCIAL CONCRETE PROJECT ON THE HORIZON?

Get a free, no-obligation quote from a team that’s handled the tricky ones.